At a glance

Most of the waiting isn't set by law. The legal clocks are short: three business days to change your mind after signing at home, 45 days for an HOA to answer, and an instant online permit in most of the state. The utility's final approval, called permission to operate (PTO), is the step people ask about most. For home solar approved in 2026, half got it within 19 days of the utility receiving the application, three in four within 65 days, and nine in ten within 147 days.

Don't turn the system on before that approval arrives in writing: PG&E says so for safety reasons.

Every step and its clock

StepWhose clockHow longRule
SigningYou and the company3 business days to cancel a contract signed anywhere but the company's place of business; 5 if you're 65 or olderCivil Code 1689.6; Bus. & Prof. Code 7159
HOA approvalYour HOAMust deny in writing within 45 days of getting the application, or it's approvedCivil Code 714
Building permitYour city or countyIssued in real time online where a platform covers the system; review limited to health and safetyGov. Code 65850.52, 65850.5
InstallationYour contractorNo legal clock. It must be a licensed contractorBus. & Prof. Code 7048
InspectionYour city or countyOne inspection for a rooftop system up to 10 kW AC on a house or duplexGov. Code 65850.5(h)
Permission to operateYour utilityPG&E: typically 5 to 10 business days once it has the paperwork; SCE: within 10 for simple solar-only requests. Median 19 days from first application in 2026Utility pages; DG Stats

The installation itself has no legal deadline. Our data starts at the utility application, so it can't say how many days pass between signing and filing.

Permission to operate: what 2026 approvals took

The spread is wide. A quarter of approvals came within 5 days, but one in five (18%) took more than 90. SCE was the fastest of the three at the median, 12 days; PG&E's median was 27 and SDG&E's 30.

The wait has moved a lot. SCE's median climbed to about 40 days through spring 2025 and fell to 6 by August 2026. PG&E's peaked at 48 days in March 2026, then dropped to about 10 by summer. SDG&E's has mostly run 20 to 36 days since January 2025.

Why the numbers differ

The utilities' own figures are much shorter than the medians above. For July to September 2026, the state's published quarterly report gives an average "interconnection time" of 5.1 days for PG&E, 5.5 for SCE and 2.4 for SDG&E, for homes. The application data counts something wider: every day from the first time the utility receives the application to the PTO letter. That can include days the utility doesn't control.

A technician's gloved hand on a disconnect switch beside two utility meters on a stucco wall
PG&E5 to 10 business days

after PG&E receives the paperwork (application, single line diagram, copy of the final building permit), up to a maximum of 30 business days. PG&E asks contractors to file the application early.

SCEWithin 10 business days

for simple, solar-only requests with every document in order, which SCE says may get permission in that time. A battery or non-standard meter needs more review.

SDG&EUnder 5 business days

on average to process an online application (within 30 days at most). SDG&E reviews the application before installation starts and emails when work can begin.

The clock starts at different points. SDG&E reviews the application before installation starts, so its count includes the installation and inspection. PG&E asks contractors to file early for the same reason, so you can start shortly after the city signs off. SCE recommends sending the application together with the final electrical permit approval. And an application with wrong information or a missing document goes back for correction: SCE emails you or your contractor with what to fix.

Does a battery slow it down?

At SCE, yes. Solar-only systems approved in 2026 had a median wait of 6 days; systems with a battery, 16. SCE says requests with paired storage need extra technical and engineering review. Most SCE approvals now include a battery, 79% of them in 2026. We can't compare the other two: in this data set PG&E's two battery fields disagree, and SDG&E's lists no batteries. Whether a battery is worth it is a separate question: see solar batteries in California.

Dates that matter in 2026 and 2027

Dec 31, 2026
Finish construction for the property tax exclusion

California's exclusion keeps a new solar system from raising your property tax assessment. The Board of Equalization says it applies to systems whose construction is completed before January 1, 2027. The letter talks about construction being finished; it doesn't mention the utility's approval. Property tax guide.

Calendar year
The year your application is complete sets your export credits

PG&E's tariff locks your export credit schedule to the year your interconnection application is completed, and its bonus credit (ACC Plus) to that year too: 0.88 cents per kWh for 2026 applications, 0.44 cents for 2027. A complete application in December and one in January land in different years.

Nine years from PTO
A slow approval doesn't shorten the lock

PG&E's tariff counts the nine years of locked credits from the day permission to operate is issued, not from the application, so time spent waiting for approval doesn't eat into them.

Dec 31, 2027
The last day to apply for a locked schedule

Applications completed after 2027 get no nine-year schedule: their credits follow each year's current values, and the bonus credit ends. The CPUC says PG&E and SCE homes that apply before the end of 2027 get it.

An installer in blue coveralls and bright gloves fastening a solar panel clamp with a cordless drill

Keeping it on track

  • Apply to your HOA early. It has up to 45 days to answer in writing.
  • Sign the interconnection agreement when it arrives. It's one of the steps in PG&E's process, and SCE recommends sending the signed agreement with the application.
  • Put your email on the application. PG&E says you can get approval faster by email.
  • Plan around a battery. At SCE, paired storage means more review and, in 2026, a longer median wait.
  • Don't switch it on early. Wait for the written permission to operate. PG&E's engineering review can also find grid upgrades that cost money and add time.
Next step

What a free quote call gets you

  • One verified local installer
  • The installed price for your roof
  • Your payback years from that price
  • Free, with no obligation

See what solar could save you

About a minute, and no phone number needed. If the number looks good, a free quote call gets you the exact price.

Check my savings →

Common questions

How long does it take to go solar in California?

The legal steps are short: 3 business days to cancel a home-signed contract (5 if you're 65 or older), 45 days for an HOA to answer, and an instant online permit in most cities. For home solar approved in 2026, the utility's permission to operate came within a median of 19 days of the application, and within 147 days for nine in ten.

How long does PG&E take to give permission to operate?

PG&E says permission typically takes 5 to 10 business days after it receives the paperwork, up to a maximum of 30 business days. Counted from the day the application was first received, PG&E's median for home solar approved in 2026 was 27 days.

How long does SCE take for PTO?

SCE says simple, solar-only requests with every document in order may get permission to operate within 10 business days, and batteries need more review. In 2026 the median from application to approval was 6 days for solar alone and 16 days with a battery.

How long does SDG&E take to approve solar?

SDG&E says it processes online applications within 30 days, in under five business days on average, and reviews them before installation starts. Because of that, its median from application to permission to operate, 30 days in 2026, includes the installation.

How long does a solar permit take in California?

Where a city or county has an online automated platform such as SolarAPP+, a licensed contractor gets the permit in real time. 379 of the 458 cities and counties the law covers reported one to the Energy Commission as of October 20, 2026.

Can I turn on my solar before permission to operate?

No. PG&E says not to turn the system on until it gives written permission to operate, for safety reasons.

Application days are counted from the state's data set and can include time before installation. Your own wait depends on your city, your HOA, your contractor's paperwork and your utility. Sources: California DG Stats: Interconnected Applications Data Set and quarterly interconnection times · PG&E: Getting started with solar · SCE: Solar Billing Plan FAQs · SDG&E: Solar and battery installation center · PG&E Schedule NBT (net billing tariff) · CPUC: Net energy metering and net billing · Board of Equalization: Letter to Assessors 2024/031 · Government Code 65850.5 · CEC: Residential Solar Permitting dashboard. Reviewed October 2026.